Which work needs a permit-to-work?
Demolition, digs over 1.5 m, crane lifts, piling and tunnelling need a permit from the project manager
Key points
- Five types: demolition; digs over 1.5 m; tower, mobile, crawler crane lifts; piling; tunnelling
- The occupier appoints a project manager and safety assessor
- Supervisor applies → assessor inspects and endorses → PM issues
- Post on site; renew if overrun
- Confined spaces and work at height have their own permits