New fire rules for timber scaffolds and safety nets
From 1 Jan 2027 timber scaffolds last 3 months; nets on projects awarded from 1 Mar 2027 must be fire-retardant
Key points
- Regulation 41: timber scaffolds may be used for 3 months, down from 9, from 1 Jan 2027. One erected before that day may still be used for up to 9 months
- If it must stay longer for a technical reason and no other scaffold will do, the occupier applies in writing to the Commissioner for a case-by-case exemption, before erection or as soon as reasonably practicable
- Regulation 23 requires netting around external scaffolds. On projects awarded on or after 1 Mar 2027, that netting must meet the Commissioner’s fire-retardant specifications
- The WSH Act Fifth Schedule will add scaffold netting, so manufacturers and suppliers must have it tested. Any one standard in the table is accepted
- Contractors and occupiers need not run the fire test. Get the report from the manufacturer or supplier before installation, and keep it on site for MOM. Every net needs an identification or batch number that traces to the report
- From 1 Mar 2028, the netting must also be certified by a body accredited by the Singapore Accreditation Council
| NFPA 701:2023 | Flame propagation of textiles and films, Test Method 2 |
| BS 5867-2:2008 | Curtain fabric flammability, Type B |
| JIS L 1091:1999 | Category 3 of Method A-1 or A-2, and Category 2 of Method D |