When does a progress payment fall due?
Construction: max 35 days, 14 if silent; supply: max 60, 30 if silent
Key points
- Construction contract with a term: at most 35 days
- No term: due after 14 days
- Counted from the tax invoice (GST-registered) or the payment response deadline
- Supply contracts: max 60 days, 30 days if silent, from the claim
- Late payment carries interest
| Construction | Max 35 days · 14 if silent |
| Supply | Max 60 days · 30 if silent |