What are TOP and CSC?
No. A TOP or CSC is needed before occupation; the project's QP applies
Key points
- A TOP or CSC is required to occupy a building or part of it
- CSC: all statutory requirements met; TOP: fit to occupy, with items outstanding
- The project QP applies, with supervision and completion certificates and agency clearances
- TOP and CSC: within 7 working days
- Express TOP in 1 working day: S$500 up to 3,000 m², S$1,000 above